EMM was engaged for historical heritage work in the North West Rail Link Early Works Package where we ensured all works were comprehensive and completed by agreed delivery dates. This included the preparation of five archaeological assessments and research designs, regulator consultation, client liaison and archaeological excavation. We kept to a strict timeframe for the preparation of five archaeological assessments and a three-month archaeological excavation program.

EMM’s work on the project continues with Transport for NSW (TfNSW) to complete the approval conditions, including excavation reports, a public open day and site interpretation.